by Megan Aird | Nov 7, 2017 | Construction Updates
– Due to issues with Toronto Hydro overhead work, construction start was delayed from original late summer start date. – Weather permitting the site is now in a full construction program with work having recommenced on October 30th. – South side...
by Megan Aird | Jun 25, 2017 | Construction Updates
Crane Erection begins THURSDAY AUGUST 17 Sidewalk in front of 897-899 Queen only to be closed periodically during the weekday, from AUGUST 21 TO September 2 for Hydro line adjustments Sidewalk in front of 897-899 Queen only to be closed periodically during the...
by Megan Aird | Jun 22, 2017 | Construction Updates
The City has started our storm sewer connection in the northern-most (westbound) of Queen Street and should be finished by June 30. We apologize for any inconvenience this may cause.
by Megan Aird | Mar 27, 2017 | Construction Updates
Construction has begun effective today, March 27th with excavation underway. Shoring will begin on site the week of April 3rd, 2017.
by Megan Aird | Dec 1, 2016 | Construction Updates
Demolition of the existing structure commenced on November 28, 2016 and is expected to be completed on December 9, 2016. Excavation is slated to begin December 12, 2016.